Appendix A, Desiderio Park and Desiderio Homes - General Conditions
Extracted standards
7 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Noise
- Construction notification distance1,000 ft
Two weeks prior to the commencement of demolition or construction, notification shall be provided to surrounding land uses within 1,000 feet of a project site disclosing the construction schedule
- Equipment shutoff
Construction-related equipment, including heavy-duty equipment, motor vehicles, and portable equipment, shall be turned off when not in use for more than 30 minutes.
- High noise activity hours
Schedule high noise-producing construction activities between the hours of 8:00 AM and 5:00 PM to minimize disruption to sensitive uses.
- Noise BMPs within 100 feet of residential areas100 ft
When demolition or construction operations occur within 100 feet of occupied residential areas, the construction contractor(s) shall implement appropriate best management practice (BMP) noise reduction measures.
Other
- Saturday construction hours
and from 8 am to 5 pm on Saturdays.
- Sunday/holiday construction prohibition
No construction or demolition activities shall occur on Sundays or holidays.
- Weekday construction hours
Construction and demolition activities shall be limited to between the hours of 7 am to 7 pm Monday through Friday
From the ordinance
Construction and demolition activities shall be limited to between the hours of 7 am to 7 pm Monday through Friday, and from 8 am to 5 pm on Saturdays. No construction or demolition activities shall occur on Sundays or holidays.