Pasadena, California · General provision
17.61.050 Specialized CUP - Major Construction
Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Major construction CUP threshold25,000 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
exceeds 25,000 square feet of gross floor area
- Review authority threshold75,000 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
For a major project 75,000 square feet or less, the Hearing Officer shall be the initial review authority... For a major project greater than 75,000 square feet, the Planning Commission shall be the initial review authority
From the ordinance
A Conditional Use Permit shall be required for new construction of a nonresidential project or a nonresidential portion of a mixed use project that exceeds 25,000 square feet of gross floor area...