Pasadena, California · General provision

17.62.120.A.3-4

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Deadline to apply for corrective work building permit30 days

    The property owner shall apply for a building permit for the corrective work required as a result of the Certificate of Appropriateness or Design Review process within 30 days of the effective date of the Certificate of Appropriateness or Design Review decision.

  • Corrective work completion deadline12 months

    The corrective work shall be diligently pursued and completed within 12 months of the date of the stop-work order issuance.

From the ordinance

The property owner shall apply for a building permit for the corrective work required as a result of the Certificate of Appropriateness or Design Review process within 30 days of the effective date of the Certificate of Appropriateness or Design Review decision. The owner of the property shall begin the corrective work required as a result of the Certificate of Appropriateness or Design Review process within 30 days of the issuance of a building permit. The corrective work shall be diligently pursued and completed within 12 months of the date of the stop-work order issuance.
17.62.120.A.3-4