Pasadena, California · General provision

17.71.070

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Building permit issuance timeframe for rebuilding24 months

    The damaged use or structure may be rebuilt and resumed provided that a Building Permit for the reconstruction or repair is issued within 24 months after the date of destruction and the construction is diligently pursued to completion.

  • To the extent of 75 percent or less, the use or structure may be rebuilt and resumed. To an extent greater than 75 percent, or is voluntarily razed or is required by law to be razed, the use or structure shall not be resumed, except in full conformance with the current provisions of this Zoning Code.

From the ordinance

Whenever a nonconforming nonresidential use or structure is involuntarily damaged or destroyed by a catastrophic event (e.g., fire or other calamity, by act of God, or by the public enemy): 1. 75 percent or less. To the extent of 75 percent or less, the use or structure may be rebuilt and resumed. 2. Greater than 75 percent. To an extent greater than 75 percent, or is voluntarily razed or is required by law to be razed, the use or structure shall not be resumed, except in full conformance with the current provisions of this Zoning Code.
17.71.070