Chapter 22.310
Dimensional standards
Servicing
- Applies near
- Baldwin Hills
- Geographic extent
- Baldwin Hills Community Standards DistrictZoning districtA mapped area with one set of rules, identified by a code like R-1 or B-2., encompassing the oil field and surrounding neighborhoods including Ladera Heights, Windsor Hills, Oak Park, View Park, Culver Crest, Blair Hills, and Raintree.
Uses
Permitted by right12
Conditional / special use3
Prohibited1
Extracted standards
61 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Abandoned well testing
The operator shall conduct annual hydrocarbon vapor testing of areas within the oil field that contain abandoned wells.
- Abandonment plan required
Within 180 days of permanent facility shut down, the operator shall submit an abandonment plan to DOGGR and submit to the Director for review and approval a time line for facility removal, site assessment, and remediation as necessary.
- Above ground piping containment
Within one year following the effective date, or at such later date as may be approved by the Director after consultation with the Director of Public Works for good cause shown, the operator shall demonstrate to the satisfaction of the Director of Public Works that secondary containment satisfying the requirements of Section 22.310.050.C.4.c is in place.
- Accelerometer required
Within 180 days following the effective date, or as may be approved by the Director for good cause shown, the operator, in coordination with the Caltech Seismological Laboratory, shall install at the oil field and have fully operational an accelerometer as required by Section 22.310.050.D.7.
- Air monitoring plan
Within 90 days following the effective date, or at such later date as may be approved by the Director for good cause shown, the operator shall develop and deliver to the Director an air monitoring plan for review and approval satisfying the requirements of Section 22.310.050.B.4.
- Annual production reports
The operator shall deliver annual production reports to the Director and the Fire Chief.
- API standards for reworking rigs
Reworking rigs shall meet the standards and specifications of the American Petroleum Institute.
- Belt guards required
Belt guards shall be required over all drive belts on drilling, redrilling, and reworking equipment.
- Building setbackSetbackThe distance a building must be held back from a lot line. from oil storage tank50 ft
No building shall be constructed within 50 feet of any oil storage tank.
- Community Alert Notification System
Within 120 days following the effective date, or at such later date as may be approved by the Fire Chief for good cause shown, the operator shall submit to the Fire Chief for review and approval a design for the CAN System referred to in Section 22.310.050.A.1.
- Annual community meetings
The operator shall hold community meetings on an annual basis to provide updates on oil operations.
- Complaint reporting
All complaints related to oil operations received by the operator shall be reported on the same business day to the environmental compliance coordinator and to the Director.
- Conditional useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. permit required for certain uses
Provided an approved Conditional Use Permit (Chapter 22.158) has first been obtained, and while such permit is in full force and effect in conformity with the conditions of such permit, the following uses may be established: 1. Drilling or redrilling that exceeds the maximum number allowed pursuant to a Ministerial Site Plan Review; 2. Steam drive plant; and 3. New tanks with a capacity of greater than 5,000 barrels.
- Draw-down account required
The operator shall maintain a draw-down account with the Department from which actual costs will be billed and deducted for the purpose of defraying the expenses involved in the County's review and verification of the information contained in any required reports and any other activities of the County.
- Electric motors required for well pumps
All well pumping units shall be operated by electric motors.
- Emergency response plan
Within 30 days following the effective date, or at such later date as may be approved by the Fire Chief for good cause shown, the operator shall submit to the Fire Chief an emergency response plan satisfying the requirements of Section 22.310.050.A.3.
- Fire protection audit
Within 120 days following the effective date, or at such later date as may be approved by the Fire Chief for good cause shown, the operator shall complete a third-party audit of the oil field's fire protection capabilities to evaluate compliance with NFPA requirements, Title 26 (Fire Code) of the County Code, the Fire Department regulations, California Code of Regulations, and API requirements.
- Fugitive dust control plan
Within 120 days following the effective date, or at such later date as may be approved by the Director for good cause shown, the operator shall develop and deliver to the Director for review and approval a fugitive dust control plan as specified in Section 22.310.050.B.16.
- Gas plant audit
Within 120 days following the effective date, or at such later date as may be approved by the Director after consultation with the Fire Chief for good cause shown, the operator shall conduct a third-party audit of the gas plant, including the gas liquids storage and loading area, to evaluate compliance with Title 26 (Fire Code) of the County Code, API standards, the CalARP Program, and all applicable SPCC and emergency response plan requirements.
- Idle well testing
The operator shall comply with Title 14 of the California Code of Regulations, Section 1723.9, regarding testing and maintenance of idle wells
- Insurance required
The operator shall provide evidence of insurance coverage that meets County requirements as required and approved by the CEO including identifying the County and its elected and appointed officers and employees as additional insureds.
- Low-profile pumps required where feasible
Downhole submersible pumps and low-profile pumping units for production wells must be used wherever feasible.
- Enclosures around machinery
The operator shall maintain enclosures around machinery with moving parts consisting of a fence, screening, or housing.
- Maximum time to remove drilling equipment90 days
All drilling and redrilling equipment shall be removed from the site within 90 days following the completion of drilling or redrilling activities unless the equipment is to be used at the oil field within five days for drilling or redrilling operations.
- Maximum number of reworking rigs8 rigs
No more than eight reworking rigs shall be present within the oil field at any one time, unless an emergency condition requires additional reworking rigs.
- Maximum wells over 20 years600 wells
Approval through Ministerial Site Plan Review for drilling new wells shall be limited to 600 wells over 20 years, beginning on the effective date of this ordinance establishing this Chapter.
- Maximum wells per year53 wells/year
New drilling and redrilling approved through a Ministerial Site Plan Review procedure shall be limited to no more than 53 wells per year, with the maximum number of newly drilled wells of that total, limited to 45 per year, except that during the first year following the effective date of the ordinance establishing this CSD, new drilling and redrilling shall be limited to no more than 24 wells.
- Meteorological station
Within 120 days following the effective date, or at such later date as may be approved by the Director for good cause shown, the operator shall submit to the SCAQMD a design for the installation of a meteorological station at the oil field.
- Annual newsletter
The operator shall publish an informational newsletter annually, which shall contain updated information on oil operations including drilling, redrilling, maintenance, repair, and reworking activities and all recently granted Conditional Use Permits or applications filed for Conditional Use Permits for the oil field.
- Noise monitoring required
The Public Health Department shall retain an independent qualified acoustical engineer to monitor ambient noise levels in the areas surrounding the oil field as determined necessary by the Director or the Director of Public Health.
- Odor minimization plan
Within 90 days following the effective date, or at such later date as may be approved by the Director for good cause shown, the operator shall develop and deliver to the Director an odor minimization plan for review and approval satisfying the requirements of Section 22.310.050.B.3.
- Oil tank secondary containment
Within one year following the effective date, or at such later date as may be approved by the Director after consultation with the Fire Chief for good cause shown, the operator shall demonstrate to the satisfaction of the Fire Chief that secondary containment satisfying the requirements of Section 22.310.050.C.4.a is in place for all existing tank areas covered by said Subsection C.4.a.
- Ombudsperson required
The operator shall designate employees or authorized agents to serve as ombudspersons to respond to questions and concerns concerning the oil operations.
- Protect well openings
The operator shall cap, close, or protect the openings in all oil wells, test holes, and similar excavation...
- Performance bond required
Prior to issuance of the first drilling or redrilling permit pursuant to this Chapter, the operator shall provide to the Department a faithful performance bond or financial instrument in the sum to be determined by the CEO.
- New pipelines must be buried
New pipelines that remove oil or gas from the oil field shall be buried below the surface of the ground;
- Consolidate pipeline corridors
New pipeline corridors shall be consolidated with existing pipelines or electrical transmission corridors where feasible.
- Pipelines not enclosed must be underground or covered
All pipelines which are not enclosed within a fence shall be placed underground or covered with materials approved by the Fire Chief.
- Active pipeline site plan required
The operator shall submit to the Fire Chief a site plan depicting the approximate location of all active pipelines... within 30 days of the installation of any new pipelines or the relocation of an existing pipeline.
- Pipeline transport required
All oil, gas, and other hydrocarbons produced from any well in the oil field shall be shipped and transported through pipelines, except in case of an emergency or when access to a pipeline becomes unavailable.
- Limited processing operations
the only processing operations permitted at the well site shall be the dehydration of oil and gas produced from the well; the storage, handling, recycling, and transportation of such materials; and those processing operations required for water injection purposes.
- Propane bullet fireproofing
Within 90 days following the effective date, or at such later date as may be approved by the Director after consultation with the Fire Chief for good cause shown, the operator shall install fire-proofing insulation on all propane and natural gas liquids bullets within the oil field, as required by Section 22.310.050.C.2.
No refining shall be conducted within the oil field.
- Retention basins 100-year storm
Within 120 days following the effective date, or at such later date as may be approved by the Director after consultation with the Director of Public Works for good cause shown, the operator shall demonstrate to the satisfaction of the Director of Public Works that all retention basins in the oil field satisfy the 100-year storm-event requirements of Section 22.310.050.C.4.b.
- Reworking hours restricted
well reworking operations shall not be allowed after 7:00 p.m. or before 7:00 a.m., nor on Sundays or legal holidays.
- Time to remove reworking rigs7 days
Reworking rigs shall be removed from the oil field within seven days following the completion of reworking operations unless such rig will be used on another well at the oil field within five days.
- Site restoration after pipeline construction
Upon completion of pipeline construction, the site shall be restored to the approximate previous grade and condition.
- Spill containment response training
The spill containment response training and equipment required by Section 22.310.050.A.2 shall be in place no later than 90 days following the effective date.
- Tank bottom leak detection program
The operator shall design, implement, and comply with a program, approved by the Fire Chief, for controlling and detecting tank bottom leaks on all tanks at the oil field.
- Tank piping standards
All new tank piping, valves, fittings, and connections including normal and emergency relief venting, shall be installed and maintained in accordance with current American Petroleum Institute standards to the satisfaction of SCAQMD and DOGGR.
- Oil tank pressure monitoring
Within 180 days following the effective date, or at such later date as may be approved by the Director for good cause shown, the operator shall install and have fully operational the tank pressure monitoring system required by Section 22.310.050.B.6.
- Tank seismic assessment
Within 180 days following the effective date, or at such later date as may be approved by the Director after consultation with the Director of Public Works for good cause shown, the operator shall complete a seismic assessment of all tanks with a capacity greater than 5,000 barrels that contain or could contain oil.
- Tank setbackSetbackThe distance a building must be held back from a lot line. from developed area500 ft
No new storage tank, excluding a replacement tank, shall be constructed closer than 500 feet from any developed area
- Tank setbackSetbackThe distance a building must be held back from a lot line. from public road200 ft
or closer than 200 feet from a public road.
- Tank specifications
All new tanks and appurtenances shall be designed, constructed, installed, and maintained in accordance with current Title 32 (Fire Code) of the County Code, American Petroleum Institute, DOGGR, California Division of Industrial Safety, Environmental Protection Agency Standards, applicable provisions of Title 14 of the California Code of Regulations Section 1774, and applicable CalARP Program requirements.
- Throughput threshold triggering review630 barrels/day
When oil or gas throughput is less than 630 barrels per day, the Director shall conduct a public hearing to determine if shut down of the oil field or other actions are appropriate.
- Vapor recovery required
Oil, wash, and produced water tanks shall be vapor tight and shall be equipped with a vapor recovery system.
- Vibration monitoring required
The Public Health Department shall retain an independent qualified acoustical engineer to monitor vibration in the areas surrounding the oil field as determined necessary by the Director or the Director of Public Health.
- Water/brine disposal requirements
Any and all water or brine produced during pipeline construction shall either be injected in accordance with DOGGR requirements, or disposed of in accordance with other local, State or federal regulations.
- Oil field web site
The operator shall maintain and update on a regular basis an oil field web site that shall include information on oil operations at the oil field, including drilling and production activities.
- Well amortization report
Within 120 days following the effective date, or at such later date as may be approved by the Director for good cause shown, the operator shall develop and submit to the Director a well amortization report that inventories the existing wells that are located within, partially, or wholly, the setback areas specified in Section 22.310.050.B.14.
From the ordinance
All drilling and redrilling equipment shall be removed from the site within 90 days following the completion of drilling or redrilling activities unless the equipment is to be used at the oil field within five days for drilling or redrilling operations.