Grading
- Maximum import/export earth530,000 cubic yardscubic yard (cy)A unit of earth volume used in grading limits — roughly one dump-truck scoop.
A total of 530,000 cubic yards of import or export of earth shall be permitted within the Universal Studios Specific Plan area.
- Maximum on-site cutGrading (cut & fill)Reshaping land by removing earth (cut) or adding it (fill), often capped by volume.4,600,000 cubic yardscubic yard (cy)A unit of earth volume used in grading limits — roughly one dump-truck scoop.
Cumulative On-Site Grading shall not exceed 4,600,000 cubic yards of cut and 3,700,000 cubic yards of fill.
- Maximum on-site fillGrading (cut & fill)Reshaping land by removing earth (cut) or adding it (fill), often capped by volume.3,700,000 cubic yardscubic yard (cy)A unit of earth volume used in grading limits — roughly one dump-truck scoop.
Cumulative On-Site Grading shall not exceed 4,600,000 cubic yards of cut and 3,700,000 cubic yards of fill.
From the ordinance
A total of 530,000 cubic yards of import or export of earth shall be permitted within the Universal Studios Specific Plan area.