22.140.510 G
Dimensional standards
Lot
Servicing
- Geographic extent
- Applies to Zones R-1, R-2, R-3, R-4, R-5, R-A, A-1, A-2, and O-S
Extracted standards
8 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Height
- Maximum tower heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.
Tower height shall be measured from the ground to the top of the tower, excluding wind turbine generator, blades, and wind measuring devices.
Noise
- Noise limit60 dBA SEL
Noise shall not exceed 60 dBA SEL as measured at the closest neighboring inhabited dwelling.
Other
- Blade clearance20 ft
No portion of a blade shall extend within 20 feet of the ground.
- Buffer from bat roosts, etc.
No part shall be closer than 300 feet or five times the tallest wind tower height from bat roosting sites, open space easements, riparian areas, and wetlands.
- Buffer from golden eagle nest
No part shall be closer than one mile from a known golden eagle nest site.
- Guy wires
The use of guy wires shall be prohibited.
- Ridgeline visual
No system shall silhouette against the skyline above any major ridgeline when viewed from designated highways.
- SetbackSetbackThe distance a building must be held back from a lot line. from property line
Minimum distance from property line or road right-of-way shall be equivalent to the height of the system.
From the ordinance
The minimum lot size shall be 0.5 acres. Noise from a small-scale wind energy system shall not exceed 60 dBA SEL...