Louisa County Unincorporated, Virginia · General provision

Sec. 86-45

Dimensional standards

Servicing

Applies near
high-voltage transmission lines
Applies within
5,280 ft
Geographic extent
Not more than a mile from existing high-voltage transmission or distribution line rights-of-way

Uses

Conditional / special use1

Extracted standards

7 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Landscaping & trees

Other

  • Compensation to adjacent property owners per parcel per year500 dollars

    it is recommended that solar project operators provide $500.00 per parcel per year to neighboring landowners.

  • Annual contribution to county operating budget per MW0.1 pct

    Solar project operators should contribute between 0.075% and 0.125% of the county's operating budget as an annual payment per megawatt produced.

  • Must begin generating electricity within five years of project approval5 years

    Solar project applicants must begin generating electricity within five years of project approval.

  • or 6,343 acres

  • Total approved utility-scale solar facilities shall not exceed 2% of county acreage2 pct

    the total approved utility-scale solar generation facilities shall not exceed two percent of total county acreage or 6,343 acres

  • Minimum vegetative buffer around utility-scale solar projects300 ft

    Such vegetative buffers shall be a minimum of 300 feet surrounding all utility-scale solar projects.

From the ordinance

Siting agreements between the county and developer shall be required. In addition, such facilities may not locate more than a mile from existing high-voltage transmission or distribution line rights-of-way.
Sec. 86-45