Sussex County Unincorporated, Virginia · General provision

Sec. 34-910

Dimensional standards

lot requirementsSTREETMIN LOT AREA100 acMAX HEIGHT15 ftMAX LOT COVERAGE65%
Plan view of the district’s stated lot requirements. Solid line: the property line. Dashed: the setback lines the ordinance imposes; a building must stay inside the tinted envelope. Drawn from the figures extracted below — illustrative, not a survey.

Uses

Extracted standards

20 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Design

  • Support building design

    The design of support buildings and related structures shall use materials, colors, textures, screening, and landscaping that will blend the facilities to the natural setting and surrounding structures.

Environmental

Fencing & walls

Landscaping & trees

  • Buffer maintenance

    The buffer shall be maintained for the life of the facility.

  • Ground cover native vegetation

    Ground cover on the site shall be native vegetation and maintained in accordance with the landscaping plan.

  • Minimum buffer width (when using wetlands/woodlands)150 ft

    The wetlands or woodlands shall be permanently protected as a designated buffer and the overall buffer shall measure at least 150 feet.

  • Minimum landscaped strip width for new plantings50 ft

    new plantings shall be provided in a landscaped strip at least 50 feet wide.

Lighting

  • Lighting direction

    Lighting fixtures as approved by the county shall be the minimum necessary for safety and/or security purposes to protect the night sky by facing downward and to minimize off-site glare.

Noise

  • Noise compliance

    At all times, the solar facility shall comply with the county's noise regulations set forth in chapter 20, article III.

Other

  • Battery inspection frequency

    The solar facility operator or owner shall conduct regular on-site inspections of the battery units and submit a written report to the zoning administrator on their condition, at least once every six months.

  • Battery safety standards

    Battery energy storage facilities shall be constructed, maintained, and operated in accordance with national industry standards.

  • Decommissioning plan

    The applicant will submit a final decommissioning and reclamation plan in accordance with these regulations.

  • Decommissioning timeline12 months

    The site shall be graded and re-seeded or replanted within 12 months of removal of solar facilities.

  • Liability insurance

    The applicant shall provide proof of adequate liability insurance for a solar facility prior to beginning construction.

  • Vehicular access to the site shall be a minimum of 50 feet from the nearest dwelling located on adjacent property.

  • Minimum staging distance from residential dwelling200 ft

    No material and equipment laydown area, construction staging area, or construction trailer shall be located within 200 feet of any property containing a residential dwelling.

  • Post driving hours

    Driving of posts shall be limited to 7:00 a.m. to 6:00 p.m., Monday through Saturday. Driving of posts shall be prohibited on state and federal holidays.

  • Screening requirement

    The facilities, including security fencing that is not ornamental, shall be screened from the ground-level view of adjacent properties or a public street in the buffer zone.

Signage

  • Signage restriction

    No signage of any type may be placed on the facility other than notices, warnings, and identification information required by law.

From the ordinance

The minimum area of a utility-scale solar facility shall be 100 acres or more. The percent of acreage coverage shall not exceed 65 percent.
Sec. 34-910