Shenandoah County Unincorporated, Virginia · General provision

Article XXI, § 165-162 to § 165-164

Uses

Conditional / special use1

Extracted standards

14 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Requirements binding on successors

    The requirements shall be binding on any successors, assignees, current or future lessee or owner of the project.

  • Bond required prior to construction

    A bond shall be posted prior to the commencement of construction with the County and maintained thereafter, reassessed every two years based on estimated decommissioning costs.

  • Documentation required upon completion

    Upon completion of decommissioning, the project owner or manager shall provide documentation as required by the Zoning Administrator to confirm completion.

  • County may recover costs from bond

    If owner/operator fails to decommission, the County may cause decommissioning and recover costs against the bond.

  • Decommissioning plan required for large-scale energy facilities

    Large-scale energy facilities are required to have a decommissioning plan per § 165-164.

  • Decommissioning triggered by prolonged inactivity

    If the project fails to operate for a consecutive period of more than one year, the Zoning Administrator may require decommissioning, with written notice and six months to complete unless extended.

  • Plan must include decommissioning cost estimates

    Estimated decommissioning cost in current dollars and projected costs for three separate decades following, with description of how estimates were determined.

  • Plan must describe impacts on surrounding lots

    A description of the impacts, if any, on the surrounding lots when decommissioned.

  • Plan must state anticipated project life

    Anticipated life of the project.

  • Plan must detail removal of structures and materials

    The plan shall detail the proposed method and steps for removal of structures, materials, buildings, roads, cabling, electrical components, large-scale operational equipment, solid or hazardous waste, and any other associated facilities at end of life.

  • Plan must include site restoration steps

    Steps to restore the site to conditions prior to commencement, including soil stabilization, revegetation, and soil restoration per any soil quality impact analysis (SQIA).

  • Plan must include topographical site plan

    A topographical site plan of the site prior to construction, description of alterations, and restoration methods.

  • Plan must address topsoil retention/restoration

    Methods to retain or restore the existing topsoil on-site.

  • Bond retained for retrofitting

    If items are to be retrofitted for another purpose approved by the Zoning Administrator, a bond will be retained until retrofitting completed, not more than two years.

From the ordinance

The below-listed uses are required to have a decommissioning plan per § 165-164. A. Large-scale energy facilities.
Article XXI, § 165-162 to § 165-164