Article XXI, § 165-162 to § 165-164
Uses
Conditional / special use1
Extracted standards
14 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Requirements binding on successors
The requirements shall be binding on any successors, assignees, current or future lessee or owner of the project.
- Bond required prior to construction
A bond shall be posted prior to the commencement of construction with the County and maintained thereafter, reassessed every two years based on estimated decommissioning costs.
- Documentation required upon completion
Upon completion of decommissioning, the project owner or manager shall provide documentation as required by the Zoning Administrator to confirm completion.
- County may recover costs from bond
If owner/operator fails to decommission, the County may cause decommissioning and recover costs against the bond.
- Decommissioning plan required for large-scale energy facilities
Large-scale energy facilities are required to have a decommissioning plan per § 165-164.
- Decommissioning triggered by prolonged inactivity
If the project fails to operate for a consecutive period of more than one year, the Zoning Administrator may require decommissioning, with written notice and six months to complete unless extended.
- Plan must include decommissioning cost estimates
Estimated decommissioning cost in current dollars and projected costs for three separate decades following, with description of how estimates were determined.
- Plan must describe impacts on surrounding lots
A description of the impacts, if any, on the surrounding lots when decommissioned.
- Plan must state anticipated project life
Anticipated life of the project.
- Plan must detail removal of structures and materials
The plan shall detail the proposed method and steps for removal of structures, materials, buildings, roads, cabling, electrical components, large-scale operational equipment, solid or hazardous waste, and any other associated facilities at end of life.
- Plan must include site restoration steps
Steps to restore the site to conditions prior to commencement, including soil stabilization, revegetation, and soil restoration per any soil quality impact analysis (SQIA).
- Plan must include topographical site plan
A topographical site plan of the site prior to construction, description of alterations, and restoration methods.
- Plan must address topsoil retention/restoration
Methods to retain or restore the existing topsoil on-site.
- Bond retained for retrofitting
If items are to be retrofitted for another purpose approved by the Zoning Administrator, a bond will be retained until retrofitting completed, not more than two years.
From the ordinance
The below-listed uses are required to have a decommissioning plan per § 165-164. A. Large-scale energy facilities.