Rockingham County Unincorporated, Virginia · General provision
Sec. 17-1003.02(d)
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Time to obtain certificate of occupancy2 years
Certificate of occupancy must be obtained within two (2) years of commencement.
- Time to commence special useConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote.2 years
Operation shall be commenced within two (2) years of approval.
- Extension of special use permitConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote.2 years
Zoning administrator may grant one-time extension of two (2) years.
From the ordinance
Operation of the building or use of the land shall be commenced within two (2) years of the date of approval...