Botetourt County Unincorporated, Virginia · General provision

Sec. 25-447 (Solar Energy Facilities)

Dimensional standards

Extracted standards

13 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Height

Other

  • Anti-glare technology required

    Solar energy facilities shall use panels that employ anti-glare technology and anti-reflective coatings that meet or exceed industry standards, to reduce glint and glare.

  • Building and zoning permit required

    A building and zoning permit is required prior to the initiation of construction of each component of any solar energy facility.

  • Site clearing shall not exceed one hundred (100) acres for each phase of development.

  • Minimum pollinator habitat percentage10 pct

    At least ten (10) percent of the total acreage of the facility shall be cultivated in such a manner to encourage pollinator habitats in order to help maintain the rural, agricultural nature of the county.

  • Compliance with national standards

    Solar energy facilities shall comply with generally accepted national environmental protection and product safety standards for the use of solar panels and battery technologies...

  • Power lines buried

    Power and communication lines running between ground-mounted solar panels, connection points at buildings, and other related equipment shall be buried underground.

  • The project area must be enclosed by security fencing not less than six (6) feet in height and equipped with appropriate anticlimbing device such as strands of barbed wire on top of the fence.

  • Utility-scale decommissioning time12 months

    The owner or operator shall physically remove the system and restore the site no more than twelve (12) months after the date of discontinued operations.

  • Vegetative buffer width150 ft

    The buffer must consist of a landscaping strip at least one hundred fifty (150) feet wide, located within the required setbacks and shall run around the entire perimeter of the project area.

Setback

From the ordinance

A building and zoning permit is required prior to the initiation of construction of each component of any solar energy facility.
Sec. 25-447 (Solar Energy Facilities)