Botetourt County Unincorporated, Virginia · General provision

Sec. 25-571 and 25-572

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Time to issue certificate of occupancy after conformance10 days

    within ten (10) days after the erection or structural alteration

  • Maximum duration of temporary zoning approval6 months

    not exceeding six (6) months

From the ordinance

A letter of temporary zoning approval may be issued by the zoning administrator for a period not exceeding six (6) months during alterations or partial occupancy of a building pending its completion.