Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Site plan approval expiration5 years
expire five (5) years from the date of approval unless building permits have been obtained
- Extension period1 years
A single one-year extension may be given upon written request by the applicant within ninety (90) days before the expiration of the approved site plan.
From the ordinance
Approval of a site plan submitted under the provisions of this article shall expire five (5) years from the date of approval unless building permits have been obtained for construction in accordance therewith. A single one-year extension may be given upon written request by the applicant within ninety (90) days before the expiration of the approved site plan.