  • Building permit required

    No building shall be erected... without a building permit.

  • Permit validity period6 months

    such permit shall be valid for a period of six (6) months.

From the ordinance

No building shall be erected, constructed, altered, moved, converted, extended, or enlarged without the owner or owners having obtained a building permit therefor from the building inspector; such permit shall require conformity with the provisions of this ordinance. When issued, such permit shall be valid for a period of six (6) months.