Emporia, Virginia · General provision

Sec. 90-436

Extracted standards

4 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Design

Height

Other

  • Maximum generation500 kW

    Maximum generation of 500 kilowatts (500 KW).

  • The solar energy facility shall comply with all setback requirements of the district in which it is located. Regardless of whether a small-scale solar facility is accessory to another use on the lot, all small-scale solar facilities shall comply with the district's principal structure setbacks.

From the ordinance

Maximum generation of 500 kilowatts (500 KW). ... If the small-scale solar energy facility is ground-mounted or not flush-mounted on a principal or accessory building, the facility's height shall not exceed 15 feet at the tallest point. ... The lowest surface of any panel shall be a maximum of four feet above the finished grade
Sec. 90-436