Emporia, Virginia · General provision

Article III, Divisions 1-10

Extracted standards

9 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Appeal time to BZA30 days

    Appeal to the board of zoning appeals shall be taken within 30 days after the decision appealed from. (Sec. 90-201)

  • BZA hearing time90 days

    The BZA shall decide an appeal within 90 days of the filing of the appeal. (Sec. 90-202)

  • Performance bond amount110 percent

    The amount of the performance bond or other guarantee shall be 110 percent of the estimated construction cost. (Sec. 90-165)

  • Site plan approval time60 days

    Site plans shall be approved or disapproved within 60 days after official submission, or within 35 days if state agency review is required. (Sec. 90-166)

  • Site plan required for all development except certain exemptions

    All development in the city requires approval of a site plan prior to issuance of zoning permit, building permit, or certificate of occupancy, except: individually developed single-family detached dwellings, two-family dwellings, accessory structures less than 256 sq ft, filling/grading less than 10,000 sq ft with no impervious structures, and repairs with no land disturbance. (Sec. 90-162)

  • Site plan scale and sheet size

    Site plans shall be prepared to scale of 1 inch = 100 feet or larger, on 24-by-36-inch sheets. (Sec. 90-163)

  • Site plan validity period5 years

    Approval of a site plan shall expire five years after the date of approval unless building permits have been obtained. (Sec. 90-169)

  • Zoning permit required for any building or structure

    No building or other structure shall be erected, moved, expanded, structurally altered, nor shall any building, structure, or land be established or changed in use without a zoning permit. (Sec. 90-171)

  • Zoning permit validity

    An approved zoning permit becomes null and void if work has not begun within one year, and expires if not substantially completed within two years. (Sec. 90-173)

From the ordinance

General administrative and procedural requirements for permits, site plans, variances, and appeals.
Article III, Divisions 1-10