Surry, Virginia · General provision

Article 3-1400, Sec. 3-1402 through 3-1404

Dimensional standards

Servicing

Applies near
James River
Applies within
100 ft
Geographic extent
Chesapeake Bay Preservation Areas including Resource Protection Areas (RPA) and Resource Management Areas (RMA) within the James River Watershed; RPA includes tidal wetlands, nontidal wetlands, tidal shores, and a 100-foot buffer adjacent to water bodies with perennial flow.

Uses

Extracted standards

13 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Environmental

  • Land upon which agricultural activities are being conducted shall have a soil and water quality conservation assessment conducted that evaluates the effectiveness of existing practices pertaining to soil erosion and sediment control, nutrient management, and management of pesticides.

  • RPA buffer maintenance

    The RPA buffer shall be maintained in accordance with performance standards including removal of indigenous vegetation only for sight lines, access paths, woodlot management, and best management practices; pruning, path construction, removal of dead/diseased trees, and shoreline erosion control.

  • All development and redevelopment exceeding 2,500 square feet shall be subject to applicable provisions of the Subdivision Ordinance for Surry County, Erosion and Sediment Control Ordinance, and the Zoning Ordinance.

  • All land development shall minimize impervious cover consistent with the use or development proposed.

  • Preserve indigenous vegetation

    Indigenous vegetation shall be preserved to the maximum extent practicable consistent with the use or development proposed.

  • Reserve sewage disposal site required

    For new construction, provide a reserve sewage disposal site with a capacity at least equal to that of the primary sewage disposal site.

  • RMA opt-out criteria

    Lots or parcels of record within the RMA may be exempt if they do not possess a RMA feature: 100-year floodplain, nontidal wetlands not connected by surface flow, highly erodible and highly permeable soils, slopes in excess of 15 percent, or a 100-foot land adjacent to a resource protection area where none of the above exist.

  • Slope threshold for RMA opt-out15 pct

    Slopes in excess of 15 percent.

  • Seaward 50 feet of buffer no encroachment50 ft

    The encroachment may not extend into the seaward 50 feet of the buffer area.

  • RPA buffer width100 ft

    A buffer area not less than 100 feet in width located adjacent to and landward of the components listed in subsections A.1. through 4. above, and along both sides of any water body with perennial flow.

  • Septic pump-out interval5 years

    All on-site sewage disposal systems not requiring VPDES permit shall be pumped out at least once every five years.

  • Water quality impact assessment required

    A water quality impact assessment is required for any proposed land disturbance, development or redevelopment within an RPA, including any buffer area encroachment, and within an RMA when deemed necessary by the administrator.

  • Wetlands permits required

    Prior to initiating grading or other on-site land disturbing activities on any portion of a lot or parcel, all wetlands permits required by federal, state and local laws and regulations shall be obtained.

From the ordinance

A buffer area not less than 100 feet in width located adjacent to and landward of the components... The RMA includes all remaining areas of Surry County which are located within the James River Watershed.
Article 3-1400, Sec. 3-1402 through 3-1404