Dimensional standards
Extracted standards
7 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Buffer clearance around fenceline20 ft
A minimum 20 foot buffer shall be established around the perimeter of the battery energy storage system's fenceline
- Decommissioning period6 months
The decommission process shall occur within six months after the battery energy storage system permanently ceases operation.
- Security fence heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.8 ft
Battery energy storage systems shall be enclosed by a security fence at least eight feet in height
Battery energy storage systems shall not exceed a height of 30 feet
- Noise limit at occupied structure in AR55 dBA
shall not exceed 55 dBA at the outer wall of any occupied structure on an adjacent parcel in the AR district
- Noise limit at property line65 dBA
The average noise generated from the battery energy storage systems... shall not exceed a noise level of 65 dBA as measured from the property line of an adjoining parcel
- Maximum sign area4 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
The sign shall not exceed four square feet in size
From the ordinance
Battery energy storage systems shall be enclosed by a security fence at least eight feet in height