- Distance from airport1 miles
These facilities shall not be located within one mile of an airport unless the applicant submits... written certification from the FAA
- Buffer rows of evergreens4 rows
four rows of staggered evergreens ten feet apart and on 15-foot centers.
- Tree heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first. at planting5 ft
Such trees shall be at least five feet tall at the time of planting
- Expected mature heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.20 ft
expected to grow to a minimum height of 20 feet within 10 years.
- Tree spacing15 ft
on 15-foot centers
- Decommissioning period6 months
The project shall be deconstructed and removed within six months after the project sites are permanently decommissioned.
- SetbackSetbackThe distance a building must be held back from a lot line. between fence and buffer25 ft
A 25 foot setback shall be provided between perimeter security fencing and vegetative buffer for emergency access.
- Groundwater monitoring frequency5 years
Ground water monitoring shall take place every five years of the operation of the project
Ground-mounted solar energy generation facilities shall not exceed a height of 18 feet
- Security fence heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.6 ft
Such fencing shall enclose the project area at least six feet in height
- SetbackSetbackThe distance a building must be held back from a lot line. from main buildings300 ft
The project area shall be set back at least 300 feet from all abutting public rights of way and main buildings on adjoining parcels and from adjacent property lines.
- SetbackSetbackThe distance a building must be held back from a lot line. from property lines300 ft
The project area shall be set back at least 300 feet from all abutting public rights of way and main buildings on adjoining parcels and from adjacent property lines.
- SetbackSetbackThe distance a building must be held back from a lot line. from public rights-of-way300 ft
The project area shall be set back at least 300 feet from all abutting public rights of way and main buildings on adjoining parcels and from adjacent property lines.
- Vegetative buffer width300 ft
The buffer shall consist of a landscaping strip at least 300 feet wide
From the ordinance
The project area shall be set back at least 300 feet from all abutting public rights of way and main buildings on adjoining parcels and from adjacent property lines.