Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Maximum extension for reconstruction180 days
A one time extension of up to 180 additional days may be granted
- Maximum placement period12 months
The period for temporary placement of such structures shall be no more than 12 months
- Maximum units per lot1 unit
Only one temporary emergency housing unit shall be permitted on any lot of record.
- Removal days after certificate of occupancy30 days
The temporary emergency housing must be removed within 30 days after a final certificate of occupancy has been issued
From the ordinance
The period for temporary placement of such structures shall be no more than 12 months