Page County Unincorporated, Virginia · General provision
§ 125-50
Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Zoning application expiration180 days
A zoning application shall expire 180 calendar days after submittal.
- Permit issuance or refusal deadline30 days
Such approval and zoning permit shall be issued or refused within 30 days from the date of application.
- Permit expiration if work not begun180 days
A zoning permit shall expire 180 calendar days after the date of issuance if work described in any permit has not begun.
- Permit expiration if work begun2 years
If work described in any zoning permit has begun within said six-month period, said permit shall expire two years from date of issuance thereof.
- Zoning permit required for all construction and uses
No building, structure or sign shall be erected, constructed, moved, added to or structurally altered, nor shall land or structures be put to any use without a permit therefore issued by the Zoning Administrator.
From the ordinance
No building, structure or sign shall be erected, constructed, moved, added to or structurally altered, nor shall land or structures be put to any use without a permit therefore issued by the Zoning Administrator.