Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Site plan approval expiration period5 years
Approval of a site plan submitted under the provisions of this Article shall expire five years after the date of such approval unless building permits have been obtained for construction in accordance therewith.
- Site plan extension decision period30 days
The Administrator shall acknowledge the request and shall make a decision regarding the requested extension within thirty (30) days after receipt of the request.
- Site plan extension request window90 days
made within ninety (90) days before the expiration of the approved site plan
- Site plan approval extension period1 years
A single one-year extension may be given, upon written request by the applicant, to the Administrator, made within ninety (90) days before the expiration of the approved site plan.
From the ordinance
Approval of a site plan submitted under the provisions of this Article shall expire five years after the date of such approval unless building permits have been obtained for construction in accordance therewith. A single one-year extension may be given, upon written request by the applicant, to the Administrator, made within ninety (90) days before the expiration of the approved site plan.