Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Zoning permit required for building work
No building or structure shall be erected, constructed, altered, moved, converted, extended, or enlarged, without the owner or owners first having obtained a zoning permit.
- Zoning permit validity period6 months
When issued, such permit shall be valid for a period of six months unless a longer period of time is specified thereon
From the ordinance
No building or structure shall be erected, constructed, altered, moved, converted, extended, or enlarged, without the owner or owners first having obtained a zoning permit. Such permit shall require conformity with the provisions of this Ordinance. When issued, such permit shall be valid for a period of six months unless a longer period of time is specified thereon