  • Zoning permit required for building work

    No building or structure shall be erected, constructed, altered, moved, converted, extended, or enlarged, without the owner or owners first having obtained a zoning permit.

  • Zoning permit validity period6 months

    When issued, such permit shall be valid for a period of six months unless a longer period of time is specified thereon

From the ordinance

No building or structure shall be erected, constructed, altered, moved, converted, extended, or enlarged, without the owner or owners first having obtained a zoning permit. Such permit shall require conformity with the provisions of this Ordinance. When issued, such permit shall be valid for a period of six months unless a longer period of time is specified thereon