Extracted standards
9 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Construction trailer permit required
Temporary trailers require annual zoning permit.
- Dumpster duration60 days
Dumpster allowed on-site for up to 60 days.
- Dumpster location
Dumpster placed within side or rear setback, not in front setback unless approved.
- Dumpster max capacity30 cubic yardscubic yard (cy)A unit of earth volume used in grading limits — roughly one dump-truck scoop.
Dumpster max capacity 30 cubic yards or no larger than 8x8x20 feet.
- Dumpster notification3 business days
Zoning Administrator notified at least 3 business days prior to placement.
- PODS max duration60 days
PODS allowed on-site for up to 60 days.
- PODS max size8 ft
PODS unit no larger than 8x8x20 feet.
- PODS notification3 business days
Zoning Administrator notified at least 3 business days prior to placement.
- Portable restroom allowed
One portable restroom allowed on construction site for duration of project.
From the ordinance
Trailers and/or other structures used on a temporary basis for storage or offices at a building site may be permitted upon approval of a trailer permit by the Zoning Administrator... All temporary trailers and other temporary construction related structures are subject to the following provisions: