§ 325-30.2
Extracted standards
8 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Active use must begin within24 months
Any conditional rezoning request approved by the Board of Supervisors shall begin the active use of the property within 24 months of the approval...
- Cash contribution allowed
Such conditions may include a cash contribution to the County;
- Conditions must conform to Comprehensive PlanComprehensive planThe long-range policy document zoning is meant to implement; it is not itself binding law.
All such conditions shall be in conformity with the duly adopted Comprehensive Plan, if applicable.
- Conditions must relate to rezoningRezoningChanging which district applies to a parcel — a legislative act, not an administrative one.
Such conditions shall have a reasonable relation to the rezoning;
- Construction must complete within60 months
...and shall complete construction within 60 months or the property shall revert to the original zoning classification...
- No mandatory dedication of property
Such conditions shall not include mandatory dedication of real or personal property for open space, parks, schools, fire departments or other public facilities...
- Conditions must relate to physical development
No conditions shall be proffered that are not related to the physical development or physical operation of the property;
- Proffers required for conditionalConditional useAllowed only after a discretionary approval — usually a public hearing and a board vote. zoning
The applicant may make a voluntary proffering, in writing, of reasonable conditions, prior to a public hearing before the Planning Commission...
From the ordinance
It is the purpose of this section to provide a more flexible and adaptable zoning method to cope with situations found in districts through conditional zoning, whereby a zoning reclassification may be allowed subject to certain conditions proffered by the zoning applicant...