Dimensional standards

lot requirementsSTREETMIN LOT AREA2,000 sq ft
Plan view of the district’s stated lot requirements. Solid line: the property line. Dashed: the setback lines the ordinance imposes; a building must stay inside the tinted envelope. Drawn from the figures extracted below — illustrative, not a survey.

Uses

Extracted standards

10 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Design

  • Tower color/finish

    Antennas or antenna support structures shall either maintain a galvanized steel finish, or subject to any applicable standards of the FAA, be painted a neutral color, so as to reduce visual obtrusiveness.

Fencing & walls

Landscaping & trees

  • Minimum landscaped buffer width15 ft

    The standard buffer shall consist of a mix of native trees and shrubs planted in a landscaped area at least 15 feet wide outside the perimeter of the compound.

  • Minimum tree diameter to preserve8 in

    All living and diseased-free trees eight inches or larger in diameter, measured four and one-half feet from the base shall be preserved and protected during construction of wireless telecommunication facilities, except where clearing is required to accommodate the proposed facilities and vehicular access.

Lighting

Other

  • Abandonment period12 months

    At such time that any component of the wireless telecommunication facility ceases to be operated for a continuous period of 12 months, it shall be considered abandoned, and the owner of such facility shall remove same within 90 days of receipt of notice from the department of planning of the removal requirement.

  • Annual safety inspection required1 per year

    The owner of each antenna support structure shall have a safety inspection conducted annually by a registered professional engineer licensed by the Commonwealth of Virginia and a copy of the inspection report shall be filed with the department of planning by March 30.

  • Removal bond required

    The applicant shall post a bond, equivalent to the cost of removal of the antenna support structure with the director of planning.

  • All antenna support structures shall be setback 110 percent of the height of the structure from all property lines.

  • All antenna support structures must be setback 200 percent of the height of the structure to the nearest residential structure, and in no case less than 400 feet.

From the ordinance

The site shall be a minimum of 2,000 square feet excluding vehicular access areas. Speculative structures are not permitted. Commercial advertising is not permitted on any component of the wireless telecommunication facility.