Dinwiddie County Unincorporated, Virginia · General provision

Sec. 22-234.50 to 22-234.73

Dimensional standards

Uses

Extracted standards

13 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Noise

  • Noise limit

    Noise requirements for solar energy projects shall be no more stringent than noise requirements for other types of development in a commercial zoning category.

Other

  • The vegetative buffer shall be maintained at maturity at a height of not less than six feet in height.

  • The vegetative buffer shall be composed of trees or shrubs of a type which at planting shall be a minimum of four feet in height.

  • Buffer plant spacing10 ft

    The trees or shrubs shall be spaced no more than ten feet apart.

  • Decommissioning timeline after cessation12 months

    The owner or operator of a solar farm shall completely decommission the solar farm within 12 months if the solar farm ceases to generate electricity for a continuous period of 12 months.

  • All solar farms shall be fenced at a minimum around the exterior of the solar collector areas with a fence which shall be at least six feet in height.

  • Groundwater monitoring frequency5 years

    Ground water monitoring shall take place every five years of the operation of the project.

  • Liability insurance required

    The applicant shall provide proof of adequate liability insurance for a solar energy project prior to the issuance of a building permit.

  • Decommissioning removal depth36 in

    Decommissioning shall include the removal of all solar collectors, cabling, electrical components, fencing, and any other associated equipment to a depth of at least 36 inches.

  • All aspects and components of a solar farm shall meet the minimum zoning setbacks for the most restrictive zoning district of the properties surrounding the site.

  • Site plan required

    No proposed solar farm shall proceed with construction until it has been submitted to and approved by the planning director as evidenced by an approved site plan.

  • Transmission line placement

    Any new electrical transmission lines associated with a solar farm may be located either above or below ground in a manner to be least intrusive.

Signage

  • Signage restrictions

    Solar equipment shall not be used for displaying any advertising except for reasonable identification of the manufacturer or operator.

From the ordinance

Solar energy project requirements including height, setbacks, fencing, buffers, decommissioning, and monitoring.
Sec. 22-234.50 to 22-234.73