Sec. 74-747
Dimensional standards
Uses
Conditional / special use1
Extracted standards
9 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Environmental
- Land disturbance plan required
A land disturbance plan shall be prepared by an engineer, submitted by the applicant, and approved by the Commonwealth of Virginia Department of Environmental Quality and the Peter Francisco Soil & Water Conservation District prior to any land disturbance.
- Wetlands avoided
Wetlands shall be inventoried, delineated, and avoided.
Lighting
- Light shielding
All outdoor lighting shall be shielded to direct light and glare onto the system's premises.
Other
- Decommissioning plan required
A decommissioning plan shall be prepared by the professional engineer and shall include the anticipated life of the project, estimated decommissioning cost, manner of decommissioning, and surety or bond posted prior to obtaining a land disturbance permit.
- FAA compliance near airports
Any solar facilities located within five (5) nautical miles of any airport shall meet all FAA requirements.
- Fire suppression plan required
Prior to generation of power, a Fire Suppression Plan shall be approved by the Cumberland County Fire Marshall, Director of Cumberland Fire & EMS, and the Cumberland County Building Official.
- Minimum solar facility fence heightMaximum heightThe tallest a building may be, given in feet, in storeys, or both — whichever binds first.6 ft
The solar facility shall be enclosed around the perimeter by a security fence with a minimum height of six (6) feet.
- No reflected glare at property line
The solar facility shall be installed so that no reflected glare is visible at the property line adjacent to a public road.
- Underground distribution lines
To the extent reasonably practical, all new distribution lines to any building, structure, or utility connection shall be located underground (trenched) to the extent permitted by the electric company.
From the ordinance
Setbacks. With the exception of poles and lines necessary to connect to the power grid, the perimeter of the system shall be located at least fifty (50) feet from the property line of any adjoining parcel owned by any landowner other than the owner of the parcel on which the solar facility is being proposed; at least one hundred (100) feet from the nearest inhabitant residence at the time of the initial application; and at least one hundred (100) feet from any public road. Height. ... the height of structures and arrays in the system shall be ground mounted and not exceed fifteen (15) feet as measured from grade at the base of the structure to the apex of the structure.