Brunswick County Unincorporated, Virginia · General provision

Sec. 23-407

Extracted standards

3 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Decommission after 6 months of inactivity6 months

    Solar facilities which have reached the end of their useful life or have not been in active and continuous service for a period of six months shall be decommissioned

  • Decommissioning plan required

    A written decommissioning agreement signed by the owner and operator and binding upon their successors and assigns shall be submitted to and approved by the board of supervisors

  • Financial assurance required

    Financial assurance of the completion of decommissioning shall be provided to the county as set forth in Virginia Code § 15.2-2241.2

From the ordinance

Solar facilities which have reached the end of their useful life or have not been in active and continuous service for a period of six months shall be decommissioned, except the board of supervisors may extend the time for the resumption of operations if the project is being repowered or a force majeure event has occurred or is occurring that will prevent the solar facility from resuming operations within six months.
Sec. 23-407