Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Days to grade and seed after demolition30 days
If a building, structure or site improvement is demolished or removed, the area shall be graded, topsoiled and seeded within 30 days
- Maximum slope for new construction30 pct
New construction on slopes in excess of 30 percent shall be prohibited
From the ordinance
New construction on slopes in excess of 30 percent shall be prohibited, unless approved by City Council pursuant to Section 21-626 or a waiver is granted by the zoning administrator pursuant to Section 21-788.