Williamsburg, Virginia · General provision

Sec. 21-777(c)

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Maximum gap in phased construction2 years

    When a site is being developed in phases, the site plan shall remain valid so long as substantial construction work does not stop for more than two years.

  • Site plan validity period5 years

    Approval of a final site plan shall be valid for a period of five years after the date of approval

From the ordinance

Approval of a final site plan shall be valid for a period of five years after the date of approval, unless a building permit has been obtained for construction; or, if a building permit has been issued and construction has not commenced, upon the expiration of the building permit.