West Point, Virginia · General provision

Sec. 70-470

Extracted standards

6 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Balloon test required

    At least three weeks prior to the planning commission meeting, the applicant shall conduct a balloon test that simulates the height of the proposed WCF.

  • Co-location efforts required

    The applicant shall allow other users to locate on the tower and site and shall provide the town, upon request, verifiable evidence of having made good faith efforts to allow such locations.

  • Conceptual plan required

    A site plan, drawn to scale, shall be submitted that depicts the location of support structure(s), equipment enclosures, landscaped/vegetative buffer areas, the potential location of additional towers on the site, fences, access, and ownership and use of adjacent properties.

  • Pre-application meeting required

    Prior to the formal application for a camouflaged WCF, multi-antenna system or a tower submittal, the prospective permittee or its representatives shall attend a pre-application meeting with the zoning administrator, a member of the planning commission, and a member of town council.

  • Professional certification by Virginia-registered engineer

    The applicant shall provide certification by a Virginia-registered engineer specifying antenna height, design, structure and capacity, compliance with building code, and noninterference study.

  • Search and service area mapping

    The applicant shall provide mapping depicting the search area and intended service area with radio signal propagation map.

From the ordinance

Conceptual plan, pre-application meeting, professional certification, co-location efforts, search area mapping, balloon test.