Tappahannock, Virginia · General provision

Sec. 22-33, 22-34, 22-36, 22-43, 22-55

Extracted standards

6 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Bond retention25 pct

    This release shall provide for 25 percent of the total bond to be retained for a period of 12 months after completion of all work.

  • Resubmission after denial2 years

    No application for a special exception which has been denied wholly or in part by the Board of Zoning Appeals shall be resubmitted for a period of two years from the date of said order of denial

  • Uses requiring minor site plan

    A minor site plan shall be filed for a single-family dwelling, a duplex, a residence with an accessory apartment, any accessory building, an addition or change of a commercial or industrial structure, or for a special exception use which does not require a zoning permit.

  • Performance bond amount110 pct

    The amount of the performance bond or other guarantee shall be 110 percent of the estimated construction cost.

  • Time to commence work12 months

    If work described in any zoning permit has not begun within one year from the date of issuance thereof, said permit shall expire

  • Time to complete work30 months

    If the work described in any zoning permit has not been substantially completed within two and one-half years of the date of the issuance thereof, said permit shall expire

From the ordinance

If work described in any zoning permit has not begun within one year from the date of issuance thereof, said permit shall expire; ... The amount of the performance bond or other guarantee shall be 110 percent of the estimated construction cost.