Tappahannock, Virginia · General provision

Sec. 22-43

Extracted standards

4 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Permit expiration if less than 10% of construction completed10 pct

    Less than ten percent of the total cost of all construction, erection, alteration, excavation, demolition, or similar work on any development authorized by such permits has been completed on the site.

  • Permit expiration if work discontinued1 years

    If, after some physical alteration to land or structures begins to take place, such work is discontinued for a period of one year, then the permit authorizing such work shall immediately expire.

  • Permit expiration if use not commenced1 years

    Zoning, special exception, sign, and other permits shall expire automatically if, within one year after the issuance of such permits: 1. The use authorized by such permits has not commenced

  • Maximum permit extension6 months

    The permit-issuing authority may extend for a period up to six months the date when a permit would otherwise expire

From the ordinance

Zoning, special exception, sign, and other permits shall expire automatically if, within one year after the issuance of such permits: 1. The use authorized by such permits has not commenced, in circumstances where no substantial construction, erection, alteration, excavation, demolition, or similar work is necessary before commencement of such use, or 2. Less than ten percent of the total cost of all construction, erection, alteration, excavation, demolition, or similar work on any development authorized by such permits has been completed on the site.
Sec. 22-43