- Permit expiration if less than 10% of construction completed10 pct
Less than ten percent of the total cost of all construction, erection, alteration, excavation, demolition, or similar work on any development authorized by such permits has been completed on the site.
- Permit expiration if work discontinued1 years
If, after some physical alteration to land or structures begins to take place, such work is discontinued for a period of one year, then the permit authorizing such work shall immediately expire.
- Permit expiration if use not commenced1 years
Zoning, special exception, sign, and other permits shall expire automatically if, within one year after the issuance of such permits: 1. The use authorized by such permits has not commenced
- Maximum permit extension6 months
The permit-issuing authority may extend for a period up to six months the date when a permit would otherwise expire
From the ordinance
Zoning, special exception, sign, and other permits shall expire automatically if, within one year after the issuance of such permits: 1. The use authorized by such permits has not commenced, in circumstances where no substantial construction, erection, alteration, excavation, demolition, or similar work is necessary before commencement of such use, or 2. Less than ten percent of the total cost of all construction, erection, alteration, excavation, demolition, or similar work on any development authorized by such permits has been completed on the site.