Poquoson, Virginia · General provision

Section 1-20

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Maximum permit duration365 days

    The permit established by this section, shall be issued for a period not to exceed one year.

  • Security deposit1,000 dollars

    the applicant shall post a cash escrow or letter of credit in the amount of $1,000.00

From the ordinance

The zoning administrator may authorize the temporary use of construction trailers, buildings and other temporary structures by issuance of an administrative permit.
Section 1-20