Appendix A, Site Plan Ordinance (Ord. No. 2025-7)
Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Appeal period60 days
appeal to the Madison County Circuit Court, provided that such appeal is filed with the Circuit Court within 60 days
- Maximum bond percentage10 pct
shall not exceed ten percent of the estimated construction costs
- Fire hydrants
Where public water service is available, fire hydrants and distribution systems shall be provided by the developer.
- Public water/sewer extension
Within the service areas of the Rapidan Service Authority, where public water or public sewer service is reasonably accessible such service shall be extended by the developer.
- Street design standard
All public streets and roads shall be designed and constructed to meet the state standards necessary for inclusion in the secondary system of state highways.
- Site plan validity5 years
An approved final site plan shall be valid for a period of not less than five years
From the ordinance
The site plan ordinance printed herein, adopted on July 2, 2025, was adopted to function as an appendix to the zoning ordinance.