Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Site plan approval expiration24 months
Site plan approval shall expire 24 months from the date of approval if a building permit has not been issued.
- Site plan review period60 days
The City Planner shall approve, approve with conditions, or deny the site plan within 60 days of receipt of a complete application.
From the ordinance
Site plan approval shall expire 24 months from the date of approval if a building permit has not been issued, unless the City Planner grants an extension for good cause shown.