Other
- Borehole setbackSetbackThe distance a building must be held back from a lot line. from property line100 ft
Boreholes shall not be located within 100 ft. of any property line.
- Disturbance setbackSetbackThe distance a building must be held back from a lot line. from commercial100 ft
Within 100 ft. of any commercially zoned property.
- Disturbance setbackSetbackThe distance a building must be held back from a lot line. from residential/planned development/dwelling500 ft
Within 500 ft. of any property zoned residential or planned development; or dwelling.
- Maximum drill site area4 acresacre43,560 square feet — about the size of an American football field without the end zones.
Maximum drill site of 4 acres.
- Well bore setbackSetbackThe distance a building must be held back from a lot line. from public groundwater supply well1,000 ft
No exploratory or production oil or gas well bore shall be permitted within 1,000 ft. of a public groundwater supply well.
- Well bore setbackSetbackThe distance a building must be held back from a lot line. from RPA/occupied building/dwelling/public road750 ft
No exploratory or production oil or gas well bore shall be permitted within 750 ft. of any RPA boundary, occupied building or dwelling, or a public road.
Setback
- Building setbackSetbackThe distance a building must be held back from a lot line. from public road or adjoining property200 ft
No building or structure used in connection with an extraction operation shall be located within 200 ft. of any public road or any adjoining property.
- Office building setbackSetbackThe distance a building must be held back from a lot line.100 ft
Buildings devoted solely to office and administrative uses shall be located no less than 100 ft. from a public road or adjoining property.
From the ordinance
No building or structure used in connection with an extraction operation shall be located within 200 ft. of any public road or any adjoining property. ... No exploratory or production oil or gas well bore shall be permitted within 750 ft. of any RPA boundary, occupied building or dwelling, or a public road.