King George County Unincorporated, Virginia · General provision
Section 7-5-10
Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Hours of operation
Hours of operation shall be limited to 7:00 a.m. to 8:00 p.m.
- Maximum duration per use60 days
Each use shall be permitted for a period not to exceed 60 consecutive days.
- Maximum permits per year4 permits
No more than 4 permits shall be issued for the same lot during a calendar year.
- Minimum days between permits30 days
A minimum of 30 consecutive days after a permit issued to that applicant for the same or an adjacent lot or parcel has expired.
Parking
- Parking on site
Parking shall be supplied on the site of the primary use and not along the public right-of-way.
Setback
- SetbackSetbackThe distance a building must be held back from a lot line. from public right-of-way15 ft
The outdoor sales use or display shall be setback at least 15 ft. from any public right-of-way and outside any required landscape buffer.
From the ordinance
No more than 4 permits shall be issued for the same lot during a calendar year. ... Each use shall be permitted for a period not to exceed 60 consecutive days. ... The outdoor sales use or display shall be setback at least 15 ft. from any public right-of-way.