King George County Unincorporated, Virginia · General provision

Section 4-2-4

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Maximum utility easement area10 pct

    Land restricted for building by utility easements shall be considered unusable and shall account for no more than 10% of the minimum required area on any lot.

  • Maximum water area20 pct

    Lot area for the purpose of satisfying minimum area requirements shall not include portions under water, except where the total area of a body of water is within the lot and/or constitutes less than 20% of the lot area.

From the ordinance

Land restricted for building by utility easements shall be considered unusable and shall account for no more than 10% of the minimum required area on any lot.
Section 4-2-4