Hurt, Virginia · General provision

Sec. 28-709

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Utility solar maximum distance from transmission line2 mi

    Utility-scale solar energy facilities shall be located no more than two miles from an existing electrical transmission line.

  • Utility solar maximum panel coverage70 pct

    Density of panel coverage over the entire site area shall be no more than 70 percent.

From the ordinance

Utility-scale solar energy facilities shall be permitted in the Industrial District I-1. A special use permit shall be required. ... Density of panel coverage over the entire site area shall be no more than 70 percent.
Sec. 28-709