Henrico County Unincorporated, Virginia · General provision
Sec. 24-4331
Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- CDD landfill Transitional Buffer 50
must provide a Transitional Buffer 50 around its perimeter
- Recycling processing center distance from Residential250 ft
The center must be located at least 250 feet from any Residential district or any lot on which the principal use is a dwelling.
- Salvage/junkyard distance from public right-of-way500 ft
A salvage and junkyard must not be located within 500 feet of a public right-of-way
- Sanitary landfill minimum area2,178,000 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
The minimum site area for a sanitary landfill is 50 acres.
- Solid waste transfer station distance from Residential250 ft
A solid waste transfer station must not be located within 250 feet of any Residential district or any lot on which the principal use is a dwelling.
Setback
- CDD landfill setbackSetbackThe distance a building must be held back from a lot line. from residential, school, childcare300 ft
A construction, demolition, and debris ("CDD") landfill must be set back at least 300 feet from any existing residential use, school, or childcare center
From the ordinance
A construction, demolition, and debris ("CDD") landfill must be set back at least 300 feet from any existing residential use, school, or childcare center, and must provide a Transitional Buffer 50 around its perimeter. ... The minimum site area for a sanitary landfill is 50 acres. ... A recycling processing center must be located at least 250 feet from any Residential district or any lot on which the principal use is a dwelling. ... A salvage and junkyard must not be located within 500 feet of a public right-of-way. ... A solid waste transfer station must not be located within 250 feet of any Residential district or any lot on which the principal use is a dwelling.