Henrico County Unincorporated, Virginia · General provision
Sec. 24-4314.B
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Sewage plant distance from residential400 ft
A sewage treatment plant must not be located within 400 feet of any Residential district
- Substation distance from residential100 ft
An electric substation serving a community- or region-wide area must not be located within 100 feet of any lot in a Residential district
Setback
- Power generation setbackSetbackThe distance a building must be held back from a lot line.250 ft
An electrical power generation facility must not be located within 250 feet of any lot line.
From the ordinance
An electrical power generation facility must not be located within 250 feet of any lot line.