Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Application fee for non-small cell facilities500 dollars
The application fee shall be $500.00.
- Application fee for small cell facilities100 dollars
The application fee shall be $100.00 apiece for each of the first five (5) individual permit requests included with a single application, plus $50.00 apiece for each additional individual permit request above five (5) included with a single application.
- Review timeframe for non-small cell facilities90 days
Within ninety (90) days of submittal of a complete application, the Department shall (i) approve the individual permit request; or (ii) deny the individual permit request in writing
- Review timeframe for small cell facilities60 days
Within sixty (60) days of submittal of a complete application, the Department shall, for each individual permit request included in an application: (i) approve the individual permit request; or (ii) deny the individual permit request in writing
- Wireless Infrastructure Permit required
No wireless infrastructure provider shall co-locate a small cell facility in or on any existing structure without first obtaining a Wireless Infrastructure Permit (WIP) from the Department
From the ordinance
Communication antenna, commercial building-mounted in all districts. The following minimum conditions shall be met: The following criteria regulate the use of less obtrusive support structures that are alternatives to traditional monopole and tower-based facilities, by accommodating installations on existing structures.