- Zoning permit work must begin within18 months
work described in any zoning permit has not begun within eighteen (18) months
- Zoning permit work must be substantially completed within5 years
work described in any zoning permit has not been substantially completed within five (5) years
From the ordinance
If the work described in any zoning permit has not begun within eighteen (18) months from the date of issuance thereof, said permit shall expire. If the work described in any zoning permit has not been substantially completed within five (5) years of the date of issuance thereof, said permit shall expire.