Sections 36.65-36.68
Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Appeal to BZA deadline30 days
Such appeal shall be taken within 30 days after the decision appealed from by filing with the Zoning Administrator, and with the board, a notice of appeal specifying the grounds thereof.
- Appeal to circuit court deadline30 days
A petition specifying the grounds on which the applicant is aggrieved must be submitted 30 days after the filing of the decision in the office of the BZA.
- BZA decision deadline90 days
The Board of Zoning Appeals shall fix a reasonable time for the hearing of an appeal, give public notice thereof as well as due notice to the parties in interest, and decide the same within 90 days of the filing of the appeal.
- Construction violation suit deadline15 days
construction of a building with a valid building permit deemed in violation of this Ordinance may be prevented, restrained, corrected, or abated by suit filed within fifteen days after the start of construction
From the ordinance
Such appeal shall be taken within 30 days after the decision appealed from by filing with the Zoning Administrator, and with the board, a notice of appeal specifying the grounds thereof. The Board of Zoning Appeals shall ... decide the same within 90 days of the filing of the appeal. A petition ... must be submitted 30 days after the filing of the decision. Construction ... may be prevented ... by suit filed within fifteen days after the start of construction.