Danville, Virginia · General provision

Article 12, Sections H and I

Extracted standards

5 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • As-built survey required

    Prior to issuance of an occupancy permit, a certified "as-built" survey shall be provided to the Director of Planning/Zoning Administrator upon completion of site improvements.

  • Site plan approval expiration5 years

    Final approval of any site plan (with the exception of erosion and sediment control plans) submitted under the provisions of this ordinance shall expire five (5) years after the date of such approval in accordance with the Code of Virginia, 1950, as amended, thereafter requiring re-submittal for approval.

  • Initial bond term12 months

    The period of the initial bond (surety) agreement shall be not less than twelve (12) months from its effective date.

  • Maintenance bond percentage10 pct

    The maintenance (defect) shall be in an amount and form satisfactory to the City Attorney but in no instance shall be less than ten (10) percent of the total construction cost of the improvements subject to the bond.

  • Notice before work48 hours

    The owner or developer shall notify the Director of Planning/Zoning Administrator in writing forty eight (48) hours prior to the beginning of any work shown to be constructed on an approved major or minor site plan.

From the ordinance

Final approval of any site plan ... shall expire five (5) years after the date of such approval ... The period of the initial bond (surety) agreement shall be not less than twelve (12) months ...
Article 12, Sections H and I