Article 3-1300, Sec. 3-1307, 3-1308, 3-1309, 3-1310
Dimensional standards
Extracted standards
7 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Appeal deadline to circuit court30 days
Any person aggrieved by any decision of the board of supervisors may appeal such decision to the circuit court for the County of Surry provided that such appeal is filed within 30 days after the final decision is rendered
- Appeal deadline to board of supervisors14 days
any person aggrieved by any decision of the historic architectural review committee may appeal such decision to the board of supervisors, provided that such appeal is filed within 14 calendar days
- Decision deadline100 days
The board of review shall hold a public hearing and shall take action within 100 days after receipt by the administrator.
- Delay of approval period2 years
it may delay the effective date of an approval for a period of two years to enable negotiations to be undertaken and completed for acquisition of the property for preservation or public use.
- Demolition approval required
no historic landmark, building or structure within a HP Historic District shall be razed or demolished until the razing or demolishment thereof is approved by the board of supervisors
- Review comment period30 days
At least 30 days prior to the public hearing, the administrator shall refer the application in writing to Preservation Virginia...
- HistoricHistoric districtAn area where exterior changes need design review to protect its character. review required
An application shall be submitted to the administrator for review and action by the board of review
From the ordinance
The board of review shall hold a public hearing and shall take action within 100 days after receipt by the administrator.