Dendron, Virginia · General provision
Sec. B and C (Temporary emergency housing)
Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Extension for temporary emergency housing during reconstruction180 days
A one time extension of up to 180 additional days may be granted by the administrator if substantial reconstruction of the destroyed dwelling has occurred.
- Maximum duration for temporary emergency housing12 months
The period for temporary placement of such structures shall be no more than 12 months, unless an extension is specifically authorized by the board of supervisors.
- Maximum temporary emergency housing units per lot1 unit
Only one temporary emergency housing unit shall be permitted on any lot of record.
- Removal days after final certificate of occupancy30 days
The temporary emergency housing must be removed within 30 days after a final certificate of occupancy has been issued for the reconstructed dwelling.
From the ordinance
Temporary emergency housing may be placed on property when a disaster has been declared... The period for temporary placement of such structures shall be no more than 12 months...